Commercial construction project plan

Added: Dec 28, 2009
Provided by: office.microsoft.com
Tags: foundations, roof, construction, office building, elevators. electrical
Description:

This plan represents three-story Office Building (76,000 square feet). It consists from the following phases:

- General Conditions

- Long Lead Procurement

- Mobilize on Site

- Site Grading and Utilities

- Foundations

- Steel Erection

- Form and Pour Concrete - Floors and Roof

- Carpentry Work

- Masonry Work

- Roofing

- Window wall and store front closures

- Building Finishes

- Elevators

- Plumbing

- Electrical

- Heating and Ventilating - AC

- Final Clean-up and Occupancy

- Complete Final Inspections

Tasks (click arrows to expand / collapse items): View Gantt and Resources

Commercial Construction

Three-story Office Building (76,000 square feet)

General Conditions

Receive notice to proceed and sign contract

Submit bond and insurance documents

Prepare and submit project schedule

Prepare and submit schedule of values

Obtain building permits

Submit preliminary shop drawings

Submit monthly requests for payment

Long Lead Procurement

Submit shop drawings and order long lead items - steel

Submit shop drawings and order long lead items - roofing

Submit shop drawings and order long lead items - elevator

Submit shop drawings and order long lead items - plumbing

Submit shop drawings and order long lead items - electric

Submit shop drawings and order long lead items - HVAC

Detail, fabricate and deliver steel

Mobilize on Site

Install temporary power

Install temporary water service

Set up site office

Set line and grade benchmarks

Prepare site - lay down yard and temporary fencing

Site Grading and Utilities

Clear and grub site

Stone site access and temporary parking area

Rough grade site (cut and fill)

Install storm drainage

Install exterior fire line and building fire riser

Perform final site grading

Erect building batter boards and layout building

Foundations

Excavate foundations

Excavate elevator pit

Form column piers and spread foundations

Rough-in electric and plumbing in elevator

Form elevator pit walls

Set reinforcing and anchor bolts

Pour column piers and foundations

Pour concrete elevator walls

Cure elevator wall concrete

Cure piers and foundations

Strip wall forms

Strip column piers and foundation forms

Install pneumatic tube in elevator pit

Prepare and pour concrete floor in elevator pit

Steel Erection

Erect steel columns, beams and joist - 1st and 2nd floors

Erect steel columns, beams and joist - 3rd floor and roof

Install miscellaneous iron and bracing - 1st and 2nd floors

Install miscellaneous iron and bracing - 3rd floor and roof

Install stairs and miscellaneous iron railing

Touch-up paint on steel

Form and Pour Concrete - Floors and Roof

Form 2nd floor including all floor openings

Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

Pour 2nd floor slab

Cure 2nd floor slab

Strip forms from 2nd floor slab

Form 3rd floor including all floor openings

Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

Pour 3rd floor slab

Cure 3rd floor slab

Strip forms from 3rd floor slab

Form roof slab including all floor openings

Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

Pour roof slab

Cure roof slab

Strip forms from roof slab

Form 1st floor

Install electrical underground

Install plumbing underground

Install rebar and in-floor utilities

Pour 1st floor slab

Cure 1st floor slab

Strip forms from 1st floor slab

Carpentry Work

Install exterior sheathing and metal studs

Masonry Work

Rough-in plumbing at toilets and masonry walls

Lay masonry at core, mechanical, and toilets

Install exterior masonry work

Install roof drains

Install tile in toilet rooms

Clean masonry

Clean toilet room tile

Roofing

Install flashing at parapet walls

Pour lightweight concrete roof fill

Install seamless roofing material

Spread stone ballast on seamless roof

Set rooftop equipment

Window wall and store front closures

Install window wall aluminum and glass

Install interior stud walls and drywall

Install interior doors and hardware

Install store front doors and hardware

Building Finishes

Install millwork and wood trim

Paint walls and woodwork

Install conduit at ceiling plenum space

Install duct in ceiling plenum space

Install ceiling grid

Install ceiling tile

Hang wallpaper

Install building carpet

Install hardware and accessories

Complete interior and exterior sod and plantings

Pave, curb, and stripe parking lot

Elevators

Set elevator equipment in shafts

Set equipment in mechanical room

Test and align doors and equipment

Plumbing

Rough-in plumbing in drywall walls

Tie-in fire line riser and set valves

Set plumbing fixtures and trim

Flush, test, and clean piping and fixtures

Electrical

Rough-in electrical in masonry walls

Rough-in electrical in drywall walls

Pull wire in conduit and set area transformers

Install and terminate electrical devices

Make electrical terminations for HVAC equipment

Install light fixtures - test and clean

Heating and Ventilating - AC

Set equipment in mechanical room

Rough-in mechanical in masonry walls

Rough-in mechanical in drywall walls

Install duct in building chase

Set HVAC trim and test and balance system

Final Clean-up and Occupancy

Install hard tile flooring in common areas

Clean hard tile floors

Remove debris from building and do final clean-up

Substantial completion date

Complete Final Inspections

Complete elevator inspection and certification

Perform architect's inspection

Perform local building agency inspection

Perform Fire Marshal's inspection

Complete punch list items from all inspections

Obtain certificate of occupancy

Issue final completion documents including warranties

Issue final request for payment